Progress report for the Saturday February 12, 2022 GGRM workday at Schellville
The Saturday February 12, 2022 GGRM workday was focused on the following items at the Victory Station Yard and the Sonoma Rail storage site at Schellville . The primary emphasis was on the tasks required to get the GGRM’s passenger cars ready for operation. In addition, the 92-day inspection of GP9 #3194 was also started. Thanks go out to the GGRM volunteers listed below who helped make the February 12 th Schellville workday very productive: David Waterman, Nico Dacong, Steve Coon, Steve Rusconi, Seth Adams, Burr Wilson, and Peter Schulze. Below is the progress report for the Saturday’s February 12, 2022 workday. At the Victory Station Yard worksite: 1. The GGRM EIC is required to send a text to NWPCo General Manager Ryan Martin when flag and derail protection has been set at the Victory Station Yard and the north leg of the Schellville wye. Done, Jim Prettyleaf 2. Continue working to install the new control system for the #2979 Tavern Car’s air c